Public Sector Project Coordinator
Building the BIM Mandate into a public capital project
Print / save as PDF (opens in a new tab)
New here? A persona is a short, realistic story about one person at work. Not a real person, but built from real jobs, projects and rules.
- A role
- A situation
- The steps they take
- What to learn and read
The story in three frames
What the job looked like, what changed, and where they need to get to.
Eight steps, and who hands what to whom
You lead most steps, with the Information Manager. Design teams and the contractor send you their work.
You getYou send
You
Project Coordinator
Check the BIM rules apply
Confirm the BIM rules cover both appointments, and record it in the plan.
Set the information needs
List the questions each decision needs answered, and what the school needs.
Approve information rules
Approve the standard, naming, protocol and CDE rules for every appointment.
Issue the design tender
Put the EIR and the information scoring criteria into the tender.
Receive tender responses
You receive each design team's BIM plan, capability and mobilisation plan.
Evaluate and appoint
Score the responses, report at the Project Review, appoint the teams.
Receive the information
At each stage and at handover, the design team lead submits its model.
Accept or reject
Accept or send it back, and report its status at each Project Review.
Information Manager
Drafts and advises
Design team lead
Tenders and delivers
Sanctioning Authority
Approves each gate
Main contractor
Tenders and hands over
Your choice after step 1: who will manage information for the client?
No single right answer. The Report compares the options in detail.
-
An in-house information manager
Good: direct control, independent of the teams
Watch: staff need the skills and the time
-
An independent consultant
Good: specialist skills without straining staff
Watch: extra procurement, cost and briefing
-
Hand it to the design team lead
Good: less day-to-day work for your staff
Watch: they would check their own work
-
In-house owner, bought-in support
Good: you keep control, experts fill the gaps
Watch: split the duties clearly between them
Everyone on this school project
Six personas share one made-up school project. Requirements flow down from the client; records flow back up.
The client
The design team
The main contractor
The supply chain
Requirements flow this way
Records flow back this way
What success looks like
At each stage, to handover
- Information requirements are set before procurement and included in every tender.
- How information management is resourced is decided and recorded, with the reasons.
- Tenders are scored on information management, and competent teams are appointed.
- Information roles and responsibilities are defined for each appointment.
- Information is delivered, reviewed and accepted at each CWMF stage to handover.
What you'll learn
Five short learning briefs that match the steps. Suggestions to practise, not certificates.
- 1
Confirm the mandate and set requirements
Check whether the mandate applies, and write down what the project and the school need.
240 minutes · Blended seminar · Steps 1 and 2
- 2
Set the information standard and CDE rules
Specify file naming, CDE workflows and the information protocol for public tenders.
180 minutes · Hands-on · Step 3
- 3
Write the tender EIR and judge BIM plans
Put the EIR into the tender, set scoring criteria and assess tenderers' BIM plans.
300 minutes · Case studies · Steps 4 to 6
- 4
Check and accept stage information
Check models and data against the EIR, then formally accept or reject them.
210 minutes · Demonstrations · Steps 7 and 8
- 5
Choose who manages information
Compare the four ways to resource it, and keep acceptance with the client.
180 minutes · Workshop · Step 1 decision
Keep these handy
Build Digital materials to keep open while you work.
- Process Workflows CWMF to ISO 19650-2
Lines up the information management steps with the usual CWMF stages.
Useful at steps 1, 3 and 8
- Information Management Plan – Appointing Party
Workbooks for the client's requirements, PIR, AIR and delivery planning.
Useful at steps 2 and 4
- Information Management Plan – Delivery Team
Response formats and benchmarks for judging tenderers' BIM plans.
Useful at steps 4 to 6
Courses
- Digital Construction Technology · Atlantic Technological University
- Building Information Modelling · Atlantic Technological University
- BIM Project Information Practitioner Qualification · BSI (British Standards Institution)
Picked by Build Digital; they open on the provider's website.
Words you'll meet
The jargon on this project, in plain words.
- CWMF
- Capital Works Management Framework: the stages, reviews and contracts for public building projects.
- PIR and AIR
- Project and Asset Information Requirements: what you need for decisions, and to run the school.
- EIR
- Exchange Information Requirements: what each team must deliver, how and when. It goes in the tender.
- BIM execution plan
- A team's plan for delivering the information you require. Called a BEP, or BIM plan, for short.
- CDE
- Common Data Environment: the project's shared online filing system.
- Appointing party
- The formal name for the client: here, the ETB you work for.
Want the full picture?
This overview is the first look. Open the detail when you are ready.
Full Scenario Record
A checklist for every step, the sources and evidence, and the full learning briefs.
Open the Full RecordPublic Sector Project Coordinator
I know public projects and tendering. What BIM asks of me as the client? That part is new.
A project coordinator at an Education and Training Board, managing a €14m school extension, learns to build the BIM Mandate into tenders and reviews.
- Works for
- Education and Training Board
- Organisation
- Public sector client
- Project
- €14m school extension
- BIM Mandate
- Applies
Does this sound like your job?
Good. Start with the eight steps.
Use it as a starting point, or meet the others on this project.
Browse all personas to find a closer fit.
New here? What is a persona?
A short, realistic story about one person at work. Not a real person, but built from real jobs, projects and rules.
A roleA situationThe steps they takeWhat to learn and read
The story in three frames
Swipe to see what changed.
Eight steps, and who hands what to whom
You lead most steps. The Information Manager helps; the design team and contractor deliver.
Lines marked You get and You send are what passes between you and the others.
-
1
Check the BIM rules apply
Confirm the BIM rules cover both appointments, and record it in the plan.
-
Your choice: who manages the client's information?
An in-house information manager
Good: direct control. Watch: needs skills, time.
An independent consultant
Good: ready expertise. Watch: extra cost.
Hand it to the design team lead
Good: less work for you. Watch: checks its own work.
In-house owner, bought-in support
Good: control plus skills. Watch: clear split needed.
-
2
Set the information needs
List the questions each decision needs answered, and what the school needs.
-
3
Approve information rules
Approve the standard, naming, protocol and CDE rules for every appointment.
You get the draft rules from the Information Manager
-
4
Issue the design tender
Put the EIR and the information scoring criteria into the tender.
You get the draft EIR from the Information Manager
You send the tender and EIR to each design team lead
-
5
Receive tender responses
You receive each design team's BIM plan, capability and mobilisation plan.
You get the BIM and mobilisation plans from design teams
-
6
Evaluate and appoint
Score the responses, report at the Project Review, appoint the teams.
You get the scores from the Information Manager
You send the report to the Sanctioning Authority to approve
You get the BIM plan from the main contractor
-
7
Receive the information
At each stage and at handover, the design team lead submits its model.
You get the information model from the design team lead
-
8
Accept or reject
Accept or send it back, and report its status at each Project Review.
You get a recommendation from the Information Manager
You send any rejection to the design team lead
You get handover information from the contractor
Rejected work comes back to step 7
Everyone on this school project
Requirements flow down from the client; records flow back up.
What success looks like
At each stage, to handover
- Information requirements are in every tender.
- The resourcing choice is recorded, with reasons.
- Tenders are scored and competent teams appointed.
- Each appointment has defined information roles.
- Information is accepted at each stage to handover.
What you'll learn
Five short learning briefs. Suggestions to practise, not certificates.
- 1
Confirm the mandate and set requirements
240 minutes · Blended seminar · Steps 1 and 2
- 2
Set the information standard and CDE rules
180 minutes · Hands-on · Step 3
- 3
Write the tender EIR and judge BIM plans
300 minutes · Case studies · Steps 4 to 6
- 4
Check and accept stage information
210 minutes · Demonstrations · Steps 7 and 8
- 5
Choose who manages information
180 minutes · Workshop · Step 1 decision
Keep these handy
Build Digital materials to keep open while you work.
- Process Workflows CWMF to ISO 19650-2
Match information steps to the CWMF stages.
Useful at steps 1, 3 and 8
- Information Management Plan – Appointing Party
Workbooks for the client's requirements.
Useful at steps 2 and 4
- Information Management Plan – Delivery Team
Benchmarks for judging tenderers' BIM plans.
Useful at steps 4 to 6
Courses
- Digital Construction Technology · Atlantic Technological University
- Building Information Modelling · Atlantic Technological University
- BIM Project Information Practitioner Qualification · BSI (British Standards Institution)
Picked by Build Digital; they open on the provider's website.
Words you'll meet
BIM DictionaryCWMF
Capital Works Management Framework: stages and contracts for public projects.
PIR and AIR
What you need for project decisions, and to run the school.
EIR
Exchange Information Requirements: what each team must deliver, and when.
BIM execution plan
A team's plan for delivering the information you require (BEP).
CDE
Common Data Environment: the project's shared online filing system.
Appointing party
The formal name for the client: here, the ETB you work for.
Want the full picture?
Full Scenario Record
A checklist for every step, the sources and evidence, and the full learning briefs.
Open the Full Record