Information Manager (BIM)
Establishing information management for a public client
Print / save as PDF (opens in a new tab)
New here? A persona is a short, realistic story about one person at work. Not a real person, but built from real jobs, projects and rules.
- A role
- A situation
- The steps they take
- What to learn and read
The story in three frames
What the job looked like, what changed, and where they need to get to.
Six steps, and who hands what to whom
You do the steps, with the Project Coordinator. You check what the design team lead and main contractor send.
You getYou send
You
Information Manager
Check where things stand
Review past handovers, consultant systems and files; agree who does what.
Set what the ETB needs
With estate management, write what the ETB needs to run its schools.
Put the rules in the tenders
Add the information rules, naming standard and bid scoring to tenders.
Set up and check plans
Set up the online filing system, then check the design team's plans.
Check what is delivered
Run checks on the design models and asset data against the rules.
Hand over to the school
Move checked asset records into the ETB's systems and write up lessons.
Project Coordinator
Receives what you issue
Design team lead
Lead appointed party
Main contractor
Submits as-built data
Your choice after step 5: do the models and asset data meet the requirements?
No single right answer. The Report compares the options in detail.
-
It meets every requirement
Good: accepted and moved on to the asset model
Watch: only when every check passes, never in part
-
Send it back for fixes
Good: avoids problems from accepting it in part
Watch: the whole model goes back; dates may slip
Everyone on this school project
Six personas share one made-up school project. Requirements flow down from the client; records flow back up.
The client
The design team
The main contractor
The supply chain
Requirements flow this way
Records flow back this way
What success looks like
By 01/07/2027
- Information requirements are agreed and applied the same way on every project.
- Every project uses the shared online filing process, and the ETB keeps the information.
- Standards, naming and classification are set once and used everywhere.
- Delivered work is checked before it is accepted, and the checks are kept on record.
- Project Coordinators apply the requirements without specialist help.
What you'll learn
Four short learning briefs that match the steps. Suggestions to practise, not certificates.
- 1
Set the client's information requirements
Write the ETB's organisation, asset and project requirements, tied to CWMF gates.
240 minutes · Case study workshop · Steps 1 and 2
- 2
Write tender requirements and score bids
Put the information requirements into CWMF tenders and score bidders' BIM plans.
210 minutes · Group review · Steps 3 and 4
- 3
Set up the shared system and check models
Configure the online filing system, check models and issue clear fix notices.
300 minutes · Hands-on software lab · Steps 4 and 5
- 4
Hand over asset information and close out
Check the final records and move them into the ETB's facilities systems.
180 minutes · With facilities staff · Step 6
Keep these handy
Build Digital materials to keep open while you work.
- Information Management Plan – Organisational
A template for the ETB's information rules that every department can reuse.
Useful at steps 1 and 2
- Process Workflows CWMF to ISO 19650-2
Shows where each information task falls in the familiar CWMF stages.
Useful at steps 2, 3 and 4
- Project Information Standard – File Naming
One file naming standard for everyone, following the Irish National Annex.
Useful at steps 3 and 5
Courses
- Digital Construction Technology · Atlantic Technological University
- Building Information Modelling · Atlantic Technological University
- Building Information Modelling and Digital Leadership · Atlantic Technological University
Picked by Build Digital; they open on the provider's website.
Words you'll meet
The jargon on this project, in plain words.
- CDE
- Common Data Environment: the project's shared online filing system.
- EIR
- Exchange information requirements: what the client asks each appointed firm to deliver, and how.
- OIR and AIR
- The information the ETB needs for its own decisions, and to run and maintain its schools.
- AIM
- Asset information model: the checked records the ETB keeps to run and maintain the school.
- Appointing party
- The formal name for the client, the ETB: it sets the requirements and accepts the work.
- Lead appointed party
- The formal name for the design team lead: it owns the delivery plans you check.
Want the full picture?
This overview is the first look. Open the detail when you are ready.
Full Scenario Record
A checklist for every step, the sources and evidence, and the full learning briefs.
Open the Full RecordInformation Manager (BIM)
My role is new and continues to evolve. The BIM Mandate is why the ETB needs a uniform approach now.
The Information Manager at a public education body sets the information rules, checks what the design team and main contractor deliver, and makes sure the school can use it.
- Works for
- Education and Training Board
- Organisation
- Public client
- Project
- €14m school extension
- BIM Mandate
- Applies
Does this sound like your job?
Good. Start with the six steps.
Use it as a starting point, or meet the others on this project.
Browse all personas to find a closer fit.
New here? What is a persona?
A short, realistic story about one person at work. Not a real person, but built from real jobs, projects and rules.
A roleA situationThe steps they takeWhat to learn and read
The story in three frames
Swipe to see what changed.
Six steps, and who hands what to whom
You do the steps. You check what the design team lead and the main contractor send you.
Lines marked You get and You send are what passes between you and the others.
-
1
Check where things stand
Review past handovers, consultant systems and files; agree who does what.
-
2
Set what the ETB needs
With estate management, write what the ETB needs to run its schools.
-
3
Put the rules in the tenders
Add the information rules, naming standard and bid scoring to tenders.
You send the requirements and protocol to the coordinator
-
4
Set up and check plans
Set up the online filing system, then check the design team's plans.
You get BIM and delivery plans from the design team lead
-
5
Check what is delivered
Run checks on the design models and asset data against the rules.
You get the design models from the design team lead
You get as-built asset data from the main contractor
You send a list of fixes to the design team lead, if needed
-
Your choice: does the work meet the requirements?
It meets every requirement
Good: accepted in full. Watch: every check must pass.
Send it back for fixes
Good: fixed and rechecked. Watch: dates may slip.
-
6
Hand over to the school
Move checked asset records into the ETB's systems and write up lessons.
You send the asset model and sign-off to the coordinator
Everyone on this school project
Requirements flow down from the client; records flow back up.
What success looks like
By 01/07/2027
- Requirements are agreed and applied the same way everywhere.
- Every project uses the shared filing process; the ETB keeps it.
- Standards, naming and classification are set once and used everywhere.
- Work is checked before acceptance, with the checks on record.
- Project Coordinators apply the requirements without specialist help.
What you'll learn
Four short learning briefs. Suggestions to practise, not certificates.
- 1
Set the client's information requirements
240 minutes · Case study workshop · Steps 1 and 2
- 2
Write tender requirements and score bids
210 minutes · Group review · Steps 3 and 4
- 3
Set up the shared system and check models
300 minutes · Hands-on software lab · Steps 4 and 5
- 4
Hand over asset information and close out
180 minutes · With facilities staff · Step 6
Keep these handy
Build Digital materials to keep open while you work.
- Information Management Plan – Organisational
Information rules every department can reuse.
Useful at steps 1 and 2
- Process Workflows CWMF to ISO 19650-2
Where each information task falls in CWMF.
Useful at steps 2, 3 and 4
- Project Information Standard – File Naming
One file naming standard for everyone.
Useful at steps 3 and 5
Courses
- Digital Construction Technology · Atlantic Technological University
- Building Information Modelling · Atlantic Technological University
- Building Information Modelling and Digital Leadership · Atlantic Technological University
Picked by Build Digital; they open on the provider's website.
Words you'll meet
BIM DictionaryCDE
Common Data Environment: the project's shared online filing system.
EIR
Exchange information requirements: what the client asks each firm to deliver.
OIR and AIR
The information the ETB needs for its own decisions, and to run and maintain its schools.
AIM
Asset information model: the checked records the ETB keeps to run and maintain the school.
Appointing party
The formal name for the client, the ETB: it sets the requirements and accepts the work.
Lead appointed party
The formal name for the design team lead: it owns the delivery plans you check.